NEC/NLCPR FUNDED PROJECTS:
NEC FUNDED PROJECTS:
1.Capacity augmentation of Biswanath Chariali S/S, from 2x16 to 2x40 MVA, 132/33kV (COMPLETED)
2.Capacity Augmentation of Salakati S/S, from 1x80+1x160 to 2x160 MVA(COMPLETED)NLCPR FUNDED PROJECTS:
1.132/33 kV 2X40 MVA AZARA GRID SUBSTATION.(COMPLETED)
2.132 kV SINGLE CKT KUKURMARA - AZRA LINE 4.82 CKM.(COMPLETED)
1.Capacity augmentation of Biswanath Chariali S/S, from 2x16 to 2x40 MVA, 132/33kV (COMPLETED)
2.Capacity Augmentation of Salakati S/S, from 1x80+1x160 to 2x160 MVA(COMPLETED)NLCPR FUNDED PROJECTS:
1.132/33 kV 2X40 MVA AZARA GRID SUBSTATION.(COMPLETED)
2.132 kV SINGLE CKT KUKURMARA - AZRA LINE 4.82 CKM.(COMPLETED)